Chronicle leadthrough of restoration works

16.07.2010 - 17.07.2010
Transportation and disassembling of a wooden chapel of the XIXth century in Tsypino
The chapel was transported from the village Pasynkovo of the Talitsy settlement. The transportation was organized by Polish restorers and students under the direction of R. Chelontkovskaja, architect from Gdansk, in collaboration with LLC “Electra” (director – K. Smirnov). Transportation and renovation were carried out as part of cultural relations between Poland and the Vologda region by agreement with the Department of Culture of the Vologda region, the administration of the Talitsy settlement and inhabitants of the village Pasynkovo.
12.07.2010 - 25.12.2010
The wooden church of Elijah the Prophet (1755) in Tsypino of the Kirillov district

The restoration and reconstruction of carved elements of the iconostasis were finished. 

Repair and restoration works were made by Limited Liability Company “Restoration center – architecture, manufacture, training” (general manager – A. Popov).

07.07.2010 - 25.12.2010
The central cathedral complex of the Kirillo-Belozersky monastery including the Assumption Cathedral (1497) with the northern church porch (XVI cent.) and the western extension (1791), the Church of St. Vladimir (1554)

Research center «Antiquities of the North» (director – I. Papin) carried out the restoration works of the Assumption Cathedral and the archaeological excavations inside it.

29.06.2010 - 25.12.2010
The central cathedral complex of the Kirillo-Belozersky monastery including the Assumption Cathedral (1497) with the northern church porch (XVI cent.) and the western extension (1791), the Church of St. Vladimir (1554)

The Federal State Unitary Enterprise “Interregional Science, Restoration and Art Department” (director – S. Filatov) made the restoration anti-damage works in the lower tier of the painting of the XVIIth century. Fine art restorers revealed the parts of damage on the paint layer and fastened the painting.

28.06.2010 - 25.12.2010
The central cathedral complex of the Kirillo-Belozersky monastery including the Assumption Cathedral (1497) with the northern church porch (XVI cent.) and the western extension (1791), the Church of St. Vladimir (1554)

The first stage of the restoration works was finished. In 2010 electrically heated floors, electric lighting and electrical equipment were installed.  

The repair and restoration works were made by LLC “Electra” (Director – K. Smirnov)

27.05.2010 - 25.12.2010
The Cathedral of the Nativity of the Virgin (1490) in the Ferapontov monastery

The Federal State Budgetary Research Institution “State Research and Development Institute of Restoration” (director – A. Trezvov) made the conservation of Dionisy’s frescoes.